ConcreteGauge / Vapor barrier
Vapor barrier calculator for concrete slabs
Enter the size of the slab and the size of the roll. You get the number of strips, the feet of sheeting and the rolls to buy.
Sheeting to buy
1 roll, 10 × 100 ft
3 strips laid along the long side, 66 feet of sheeting in all. Includes 10% extra for trimming and turning up at the edges.
Each strip overlaps the one before it by 6 inches. The slab is 400 square feet; the sheeting laid is 600.
Buy seam tape as well: about 40 feet for the seams, plus more for pipes and corners.
How the strips are counted
The sheeting is rolled out in strips along the longer side of the slab. Each strip overlaps the one before it, so every strip after the first covers its width less the overlap.
For a 20 × 20 foot slab with a 10 foot roll and a 6 inch overlap:
- The first strip covers 10 feet. Each one after covers 9.5 feet.
- Two strips reach 19.5 feet, which is short, so it takes 3.
- 3 strips × 20 feet = 60 feet of sheeting. With 10% extra, 66 feet: 1 roll of 100 feet.
A plain area sum would have said 400 square feet and missed the third strip.
Rolls for common slabs
Strips and rolls of 100 feet, with a 6 inch overlap and 10% extra.
| Slab | 10 ft wide roll: strips · rolls | 20 ft wide roll: strips · rolls |
|---|---|---|
| 10 × 10 ft | 1 · 1 | 1 · 1 |
| 12 × 12 ft | 2 · 1 | 1 · 1 |
| 12 × 16 ft | 2 · 1 | 1 · 1 |
| 16 × 20 ft | 2 · 1 | 1 · 1 |
| 20 × 20 ft | 3 · 1 | 1 · 1 |
| 24 × 24 ft | 3 · 1 | 2 · 1 |
| 24 × 30 ft | 3 · 1 | 2 · 1 |
| 30 × 40 ft | 4 · 2 | 2 · 1 |
Wider rolls mean fewer seams. Where one width covers the whole slab there are none at all.
What the code asks for
Under the International Residential Code, a house floor slab on the ground gets a vapor retarder between the base and the concrete: polyethylene at least 6 mil thick, or an approved equal, with the joints lapped at least 6 inches. Garages, unheated outbuildings, driveways and paths are exempt, and so are places where the building official agrees the ground does not need it.
Thicker sheet, 10 or 15 mil, is sold for the same job and resists being torn by boots and stone during the pour. Rolls come in several widths and lengths, so enter the size printed on yours.
Laying it
Turn the sheet up the inside of the forms or the walls a few inches and trim it after the pour. Tape every seam and seal round pipes with tape or a boot. Any hole is a path for damp, so patch tears before the concrete arrives.
The sheet lies on the base from the gravel base calculator; the steel from the wire mesh calculator goes on chairs above it.
Questions people ask
How much vapor barrier do I need under a slab?
Count strips, not square feet. A 20 × 20 foot slab needs 3 strips of a 10 foot roll with a 6 inch overlap: 60 feet of sheeting, or one 100 foot roll.
How much should a vapor barrier overlap?
At least 6 inches at every joint under the International Residential Code. Many makers of thicker sheet ask for more and for taped seams, so check the instructions for your product.
What thickness of plastic goes under concrete?
The residential code minimum is 6 mil polyethylene. Thicker 10 and 15 mil sheet is tougher and is widely used for the same purpose.
Do I need a vapor barrier under a garage or driveway?
The International Residential Code exempts garages, unheated accessory buildings, driveways and walks. Your local code may differ, and some owners add one to a garage anyway if the floor will be coated.
Does the vapor barrier go over or under the gravel?
Over the gravel and directly under the concrete, according to the residential code.
Where the numbers come from
- Roll sizes outside the United States: 4 × 25 m in Britain and Ireland (Permagard); 4 × 50 m with 200 mm overlaps in Australia and New Zealand (Danterr).
- Vapor retarder thickness, laps and exemptions: International Residential Code R506, summarised by Jaspector, Slab on Grade Requirements (IRC 2024). Your local code may differ.
- Bag yields: a 40 lb bag makes about 0.3 cubic feet, 50 lb about 0.375, 60 lb about 0.45 and 80 lb about 0.6 (ArcSite, Concrete Network). Brands differ a little, so check the yield printed on your bag.
- Bag yields outside the United States: in the United Kingdom and Ireland a 20 kg bag makes about 0.01 cubic metres (Blue Circle, at Travis Perkins); in Australia and New Zealand 108 bags of 20 kg make a cubic metre (Boral); in Canada a 30 kg bag makes about 0.44 cubic feet (Quikrete, at Home Depot Canada). The 25 kg figures are worked out in proportion.
- Weight: 150 lb per cubic foot for normal concrete (Omni Calculator).
Every formula on this page is checked by an automatic test each time the site is updated. Last reviewed 15 November 2026.