How much concrete for a chain link fence post?
A chain link line post in a 6 inch hole, 24 inches deep, takes 2 bags of 50 lb concrete. A terminal post in a 8 inch hole, 30 inches deep, takes 3 bags. That includes 10% extra and allows for the room the post takes up.
What to buy for one line post (1 5/8 in)
0.4 cubic feet
0.01 cubic yards, or 0.011 cubic metres. Includes 10% extra for spills and uneven ground. Without it: 0.36 cubic feet.
Mix it from bags
2 bags of 50 lb
That is 100 lb to carry and mix.
Best for this job: under one cubic yard, bags are simpler than a delivery.
| 40 lb bags | 2 |
|---|---|
| 50 lb bags | 2 |
| 60 lb bags | 1 |
| 80 lb bags | 1 |
The concrete weighs about 60 lb once poured.
The hole
- Hole
- 6 in across, 24 in deep
- Concrete round the post
- 0.36 cubic feet
- With 10% extra
- 0.4 cubic feet
Home chain link fences use two sizes of round steel post: line posts 1 5/8 inches across along the run, and terminal posts 2 3/8 inches across at the ends, corners and gates.
Chain link posts are usually bought longer than the fence is high so the extra goes in the ground: about 2 feet for line posts and 2 1/2 feet for terminal posts. That is why the worked answers here use holes 24 and 30 inches deep.
Bags of concrete per line post (1 5/8 in)
Whole bags for one post, with 10% extra and the space the post fills taken out. First in 50 lb bags, the size fast-setting mix is usually sold in:
| Hole depth | 6 in hole | 8 in hole | 10 in hole |
|---|---|---|---|
| 24 in | 2 | 2 | 4 |
| 30 in | 2 | 3 | 4 |
| 36 in | 2 | 3 | 5 |
| 42 in | 2 | 4 | 6 |
| 48 in | 3 | 4 | 7 |
The same holes in 80 lb bags:
| Hole depth | 6 in hole | 8 in hole | 10 in hole |
|---|---|---|---|
| 24 in | 1 | 2 | 2 |
| 30 in | 1 | 2 | 3 |
| 36 in | 2 | 2 | 3 |
| 42 in | 2 | 3 | 4 |
| 48 in | 2 | 3 | 4 |
And the concrete itself, in cubic feet to buy:
| Hole depth | 6 in hole | 8 in hole | 10 in hole |
|---|---|---|---|
| 24 in | 0.40 | 0.74 | 1.17 |
| 30 in | 0.50 | 0.92 | 1.46 |
| 36 in | 0.60 | 1.10 | 1.75 |
| 42 in | 0.70 | 1.29 | 2.04 |
| 48 in | 0.80 | 1.47 | 2.34 |
The post matters: a 6 inch hole 24 inches deep holds 0.39 cubic feet when empty, but only 0.36 with the post standing in it. That is 8% less concrete than the hole alone suggests.
Bags for a row of line posts
For 6 inch holes, 24 inches deep. Bags are whole, so many posts together need fewer bags than one post’s figure multiplied up.
| Posts | Cubic feet | 50 lb bags | 80 lb bags |
|---|---|---|---|
| 1 post | 0.40 | 2 | 1 |
| 5 posts | 2.00 | 6 | 4 |
| 10 posts | 4.00 | 11 | 7 |
| 20 posts | 8.01 | 22 | 14 |
| 30 posts | 12.01 | 33 | 21 |
| 50 posts | 20.01 | 54 | 34 |
How wide and deep to dig for a line post
Quikrete’s rule is a hole three times the width of the post. This post is 1 5/8 inches wide, so that is a hole about 4.88 inches across: 6 inches is the nearest size in the tables that meets it.
The same rule sets the depth at a third to a half of the post’s height above ground, plus 6 inches for a gravel base:
| Height above ground | Post in the ground | Hole with gravel |
|---|---|---|
| 4 ft | 16 to 24 in | 22 to 30 in |
| 5 ft | 20 to 30 in | 26 to 36 in |
| 6 ft | 24 to 36 in | 30 to 42 in |
| 8 ft | 32 to 48 in | 38 to 54 in |
The gravel is not concrete, so leave it out of the depth you look up in the tables. Where the ground freezes, local rules may ask for the hole to go below the frost line, so check before you dig.
Bags of concrete per terminal post (2 3/8 in)
Whole bags for one post, with 10% extra and the space the post fills taken out. First in 50 lb bags, the size fast-setting mix is usually sold in:
| Hole depth | 8 in hole | 10 in hole | 12 in hole |
|---|---|---|---|
| 24 in | 2 | 4 | 5 |
| 30 in | 3 | 4 | 6 |
| 36 in | 3 | 5 | 7 |
| 42 in | 4 | 6 | 8 |
| 48 in | 4 | 7 | 9 |
The same holes in 80 lb bags:
| Hole depth | 8 in hole | 10 in hole | 12 in hole |
|---|---|---|---|
| 24 in | 2 | 2 | 3 |
| 30 in | 2 | 3 | 4 |
| 36 in | 2 | 3 | 5 |
| 42 in | 3 | 4 | 5 |
| 48 in | 3 | 4 | 6 |
And the concrete itself, in cubic feet to buy:
| Hole depth | 8 in hole | 10 in hole | 12 in hole |
|---|---|---|---|
| 24 in | 0.70 | 1.13 | 1.66 |
| 30 in | 0.88 | 1.42 | 2.08 |
| 36 in | 1.05 | 1.70 | 2.49 |
| 42 in | 1.23 | 1.98 | 2.91 |
| 48 in | 1.40 | 2.26 | 3.32 |
The post matters: a 8 inch hole 30 inches deep holds 0.87 cubic feet when empty, but only 0.8 with the post standing in it. That is 8% less concrete than the hole alone suggests.
Bags for a row of terminal posts
For 8 inch holes, 30 inches deep. Bags are whole, so many posts together need fewer bags than one post’s figure multiplied up.
| Posts | Cubic feet | 50 lb bags | 80 lb bags |
|---|---|---|---|
| 1 post | 0.88 | 3 | 2 |
| 5 posts | 4.38 | 12 | 8 |
| 10 posts | 8.75 | 24 | 15 |
| 20 posts | 17.51 | 47 | 30 |
| 30 posts | 26.26 | 71 | 44 |
| 50 posts | 43.77 | 117 | 73 |
How wide and deep to dig for a terminal post
Quikrete’s rule is a hole three times the width of the post. This post is 2 3/8 inches wide, so that is a hole about 7.13 inches across: 8 inches is the nearest size in the tables that meets it.
The same rule sets the depth at a third to a half of the post’s height above ground, plus 6 inches for a gravel base:
| Height above ground | Post in the ground | Hole with gravel |
|---|---|---|
| 4 ft | 16 to 24 in | 22 to 30 in |
| 5 ft | 20 to 30 in | 26 to 36 in |
| 6 ft | 24 to 36 in | 30 to 42 in |
| 8 ft | 32 to 48 in | 38 to 54 in |
The gravel is not concrete, so leave it out of the depth you look up in the tables. Where the ground freezes, local rules may ask for the hole to go below the frost line, so check before you dig.
Setting a whole fence
The fence post calculator counts the posts from the length of the fence and the spacing, then the bags for all of them. For holes or posts of another size, use the post hole calculator.
Questions people ask
How much concrete do I need for a chain link fence post?
A line post in a 6 inch hole 24 inches deep takes 0.4 cubic feet, which is 2 bags of 50 lb. A terminal post in a 8 inch hole 30 inches deep takes 0.88 cubic feet, or 3 bags of 50 lb. Both include 10% extra.
Do chain link line posts need concrete?
Many installers set every post in concrete; some set only the terminal posts in concrete and drive the line posts. The terminal posts carry the pull of the stretched fence, so they are the ones that always get it. Follow the fence maker’s instructions for yours.
How deep should chain link fence posts be?
Residential posts are sold about 2 feet longer than the fence height for line posts and 2 1/2 feet longer for terminal posts, and that extra length goes in the ground. Where the ground freezes, local rules may require the footing to go deeper.
Why is the hole for a terminal post bigger?
It is a wider post and it carries more load. At three times the post width, a 1 5/8 inch line post wants a hole about 4.88 inches across and a 2 3/8 inch terminal post about 7.13 inches.
Where the numbers come from
- Volume: (area of the hole − area of the post) × depth of the concrete.
- Chain link post sizes and lengths: 1 5/8 inch line posts and 2 3/8 inch terminal posts; line posts about 2 feet longer than the fence is high and terminal posts about 2 1/2 feet longer (Hoover Fence, residential chain link posts).
- Hole width and depth rule: Quikrete, Setting Posts in Concrete.
- Bag yields: a 50 lb bag makes about 0.375 cubic feet (Concrete Network), a 60 lb bag about 0.45 and an 80 lb bag about 0.6 (ArcSite). Brands differ a little, so check the yield printed on your bag.
Every number on this page is worked out by the same tested code as the calculators. Last reviewed 15 November 2026.