A 16 × 24 foot slab 4 inches thick takes 4.74 cubic yards of concrete. Buy 5.21 cubic yards to allow 10% for spills and uneven ground: 235 bags of 80 lb, or a 5.25 cubic yard ready-mix order.

What to buy for a 16 × 24 ft slab, 4 in thick

5.21 cubic yards

140.8 cubic feet, or 3.99 cubic metres. Includes 10% extra for spills and uneven ground. Without it: 4.74 cubic yards.

Mix it from bags

235 bags of 80 lb

About $1,527.50. That is 18,800 lb to carry and mix.

Order ready-mix

5.25 cubic yards

About $787.50 before delivery fees. Rounded up to the next quarter yard, the way suppliers sell it.

Best for this job: over one cubic yard, a truck saves a lot of mixing.

Bags needed, by bag size
40 lb bags470
50 lb bags376
60 lb bags313
80 lb bags235

The concrete weighs about 21,120 lb once poured.

The slab

24 ft16 ft4 in thick
Area
384 square feet (35.67 m²)
Round the edge
80 feet
Corner to corner
28 ft 10 1/8 in

Measure both diagonals of your forms. When each one reads 28 ft 10 1/8 in, the corners are square.

Change the size or thickness

A 16 × 24 slab at other thicknesses

Concrete for a 16 × 24 foot slab from 3 to 8 inches thick. The cubic yards and bags include 10% extra. The truck order is rounded up to the next quarter yard, and the weight is the finished slab.

ThickBuy, cu yd80 lb bagsTruck order, cu ydSlab weighs, lb
3 in3.911764.0014,400
4 in5.212355.2519,200
5 in6.522946.7524,000
6 in7.823528.0028,800
8 in10.4347010.5038,400

Four inches is the standard thickness for residential slabs such as patios and walkways. Slabs that carry vehicles or heavy loads are poured thicker, and the thickness of anything load-bearing is set by your local building code.

If this slab is a garage floor or a patio, the garage floor calculator and the patio calculator ask the questions that job has and start from its usual thickness.

Bags or a truck for a 16 × 24 slab?

At 4 inches thick this slab takes 5.21 cubic yards with the extra, so order 5.25 cubic yards of ready-mix. That fits on one truck: a full truck carries about 10 cubic yards.

From bags it would be 235 bags of 80 lb, which is 18,800 lb (9.4 US tons) to lift and mix. At this size bags are not practical: the first batches would be setting before the last were mixed.

What the concrete costs

Concrete only, at example prices of $6.50 for an 80 lb bag and $150.00 a cubic yard for ready-mix, before delivery fees. Labor, forms, base and steel are not included.

ThicknessFrom bagsReady-mix
4 in$1,527.50235 bags$787.505.25 yd$2.05 a sq ft
6 in$2,288.00352 bags$1,200.008 yd$3.13 a sq ft

Prices differ a lot from one area to the next. Put your own in the concrete cost calculator.

The rest of the list for a 16 × 24 slab

What usually goes under, round and into a slab this size. Each amount includes 10% extra and is worked out for the settings in grey. Open an item’s calculator to change them.

24 ft16 ftDashed lines: joints

Not every slab needs every item. Whether yours needs steel, a vapor barrier or a thicker base depends on the ground, the load and your local code.

Questions people ask

How many yards of concrete do I need for a 16 × 24 slab?

A 16 × 24 foot slab 4 inches thick takes 4.74 cubic yards of concrete. With 10% extra for spills and uneven ground, buy 5.21 cubic yards. At 6 inches thick it is 7.82 cubic yards with the same extra.

How many bags of concrete do I need for a 16 × 24 slab?

At 4 inches thick you need 235 bags of 80 lb or 313 bags of 60 lb, including 10% extra. At 6 inches thick you need 352 bags of 80 lb or 470 of 60 lb.

How much does the concrete for a 16 × 24 slab cost?

At example prices of $6.50 for an 80 lb bag and $150.00 a cubic yard for ready-mix, a 4 inch slab costs about $1,527.50 in bags or $787.50 in ready-mix before delivery fees. Prices vary a lot by area, so put your own in the cost calculator.

How much does a 16 × 24 concrete slab weigh?

About 19,200 lb at 4 inches thick and 28,800 lb at 6 inches, at 150 lb per cubic foot for normal concrete.

Does a 16 × 24 slab need control joints?

Yes. At 4 inches thick, joints should be no more than about 10 feet apart, so a 16 × 24 foot slab gets 3 joints, which divide it into 6 panels of 8 × 8 feet.

Where the numbers come from

Every number on this page is worked out by the same tested code as the calculators. Last reviewed 15 November 2026.