ConcreteGauge

ConcreteGauge / Slab sizes / 10 × 10 ft

How much concrete for a 10 × 10 slab?

A 10 × 10 foot slab 4 inches thick takes 1.23 cubic yards of concrete. Buy 1.36 cubic yards to allow 10% for spills and uneven ground: 62 bags of 80 lb, or a 1.5 cubic yard ready-mix order.

What to buy for a 10 × 10 ft slab, 4 in thick

1.36 cubic yards

36.67 cubic feet, or 1.04 cubic metres. Includes 10% extra for spills and uneven ground. Without it: 1.23 cubic yards.

Mix it from bags

62 bags of 80 lb

About $403.00. That is 4,960 lb to carry and mix.

Order ready-mix

1.5 cubic yards

About $225.00 before delivery fees. Rounded up to the next quarter yard, the way suppliers sell it.

Best for this job: over one cubic yard, a truck saves a lot of mixing.

Bags needed, by bag size
40 lb bags123
50 lb bags98
60 lb bags82
80 lb bags62

The concrete weighs about 5,500 lb once poured.

The slab

10 ft10 ft4 in thick
Area
100 square feet (9.29 m²)
Round the edge
40 feet
Corner to corner
14 ft 1 3/4 in

Measure both diagonals of your forms. When each one reads 14 ft 1 3/4 in, the corners are square.

Change the size or thickness

A 10 × 10 slab at other thicknesses

Concrete for a 10 × 10 foot slab from 3 to 8 inches thick. The cubic yards and bags include 10% extra. The truck order is rounded up to the next quarter yard, and the weight is the finished slab.

ThickBuy, cu yd80 lb bagsTruck order, cu ydSlab weighs, lb
3 in1.02461.253,750
4 in1.36621.505,000
5 in1.70771.756,251
6 in2.04922.257,500
8 in2.721232.7510,001

Four inches is the standard thickness for residential slabs such as patios and walkways. Slabs that carry vehicles or heavy loads are poured thicker, and the thickness of anything load-bearing is set by your local building code.

If this slab is a patio or a shed base, the patio calculator and the shed base calculator ask the questions that job has and start from its usual thickness.

Bags or a truck for a 10 × 10 slab?

At 4 inches thick this slab takes 1.36 cubic yards with the extra, so order 1.5 cubic yards of ready-mix. That fits on one truck: a full truck carries about 10 cubic yards.

From bags it would be 62 bags of 80 lb, which is 4,960 lb (2.48 US tons) to lift and mix. It can be done with a mixer and help, but the truck pours the whole slab in one go. Ask about small-load fees, which many suppliers add to short orders.

What the concrete costs

Concrete only, at example prices of $6.50 for an 80 lb bag and $150.00 a cubic yard for ready-mix, before delivery fees. Labor, forms, base and steel are not included.

ThicknessFrom bagsReady-mix
4 in$403.0062 bags$225.001.5 yd$2.25 a sq ft
6 in$598.0092 bags$337.502.25 yd$3.38 a sq ft

Prices differ a lot from one area to the next. Put your own in the concrete cost calculator.

The rest of the list for a 10 × 10 slab

What usually goes under, round and into a slab this size. Each amount includes 10% extra and is worked out for the settings in grey. Open an item’s calculator to change them.

Not every slab needs every item. Whether yours needs steel, a vapor barrier or a thicker base depends on the ground, the load and your local code.

Questions people ask

How many yards of concrete do I need for a 10 × 10 slab?

A 10 × 10 foot slab 4 inches thick takes 1.23 cubic yards of concrete. With 10% extra for spills and uneven ground, buy 1.36 cubic yards. At 6 inches thick it is 2.04 cubic yards with the same extra.

How many bags of concrete do I need for a 10 × 10 slab?

At 4 inches thick you need 62 bags of 80 lb or 82 bags of 60 lb, including 10% extra. At 6 inches thick you need 92 bags of 80 lb or 123 of 60 lb.

How much does the concrete for a 10 × 10 slab cost?

At example prices of $6.50 for an 80 lb bag and $150.00 a cubic yard for ready-mix, a 4 inch slab costs about $403.00 in bags or $225.00 in ready-mix before delivery fees. Prices vary a lot by area, so put your own in the cost calculator.

How much does a 10 × 10 concrete slab weigh?

About 5,000 lb at 4 inches thick and 7,500 lb at 6 inches, at 150 lb per cubic foot for normal concrete.

Does a 10 × 10 slab need control joints?

Not at 4 inches thick. Joints are spaced up to about 10 feet apart for that thickness, and no side of this slab is longer than that. A thinner slab needs them closer together.

Where the numbers come from

Every number on this page is worked out by the same tested code as the calculators. Last reviewed 15 November 2026.

Sizes close to 10 × 10